Construction Scheduling Software for GCs and Owners

Shackleton keeps your master schedule, critical path, and three-week look-aheads in the same system as each job’s field reports, RFIs, and budget. Built for GCs, subs, owners, and developers.

Construction site at dawn with tower crane lifting steel beam, superintendent in hi-vis vest watching from ground level.

Trusted by companies building the future

Construction Scheduling Software Built Into the Job Record

Construction scheduling software holds the plan for when each part of a job happens and in what order. In Shackleton, the schedule sits in the same project record as the budget, RFIs, and daily reports, so the office and the field work from one set of dates.

  • Gantt Charts and Milestones

    Lay out activities, durations, and dependencies, with the milestones your owner tracks.

  • Critical Path

    Shackleton calculates the critical path from your dependencies, so you see which activities set the finish date and which have room to slip.

  • Three-Week Look-Aheads

    Give each trade a near-term plan drawn from the master schedule.

  • Owner View

    Owners and multi-site operators see milestone status across every job without calling the builder.

Shackleton project schedule: a Gantt chart of the build sequence with the Shackleton AI panel recapping the day's RFIs and submittals alongside it.
Figure 1: A project schedule in Shackleton, with the day’s recap beside it.

The product page shows the modules the schedule connects to, from bid management to the Communication Hub.

From the Master Schedule to the Three-Week Look-Ahead

The three-week look-ahead is where the master schedule meets the crews doing the work. In Shackleton, the plan goes out to the trades and progress comes back to the schedule in four steps.

  1. 01

    Set the Master Schedule

    The project manager sets the logic, durations, and milestones for the whole job.

  2. 02

    Pull Each Trade’s Look-Ahead

    Each subcontractor’s next three weeks come from the master schedule, in the same sequence.

  3. 03

    Update From the Field

    A superintendent’s daily log updates the schedule automatically, and Shackleton’s agents flag an unanswered RFI about to delay a trade.

  4. 04

    Read the Day’s Recap

    Shackleton’s agent summarizes what changed that day, from new RFIs to submittals, beside the schedule.

Results From Running on One System

Shackleton powers construction teams across 15+ states, managing over $1 billion in project value. It started inside Ernest, a general contractor that kept its construction schedule in Microsoft Project, its bids and accounting in other tools, and its project managers busy keeping them in sync.

$35M

annual revenue as a self-performing commercial GC

Ernest

15 hrs

a week per project manager moving data between tools before

Ernest

Original data

Ernest was a self-performing GC, and its project managers each spent about 15 hours a week moving data between the schedule, bid, and accounting tools. Once the company ran on one system, revenue per project manager roughly doubled with the same team.

Method: the founders’ own account of running Ernest, published in What I Learned Running a $35M General Contractor (July 2026).

Shackleton changed how we think about running our business. We went from chasing paperwork to actually leading our projects.

Emmanuel N.

Chief Growth Officer, ProMD Health

I never knew what was happening on my jobs before Shackleton and I was constantly calling my builder. Now I know exactly what’s going on without having to ask any questions.

Matt G.

Ops Manager, Multi-Brand Franchise Operator

See Your Schedule in Shackleton

Walk through a live project schedule with our team, from the master schedule to this week’s look-ahead.

About Shackleton

Shackleton is the agentic platform for construction, built for general contractors, subcontractors, owners, and developers. It covers the job from estimating and bidding through closeout and syncs costs with QuickBooks, Sage, and more. Its custom agents take on one stage of the job apiece, doing the grunt work of moving data between systems and flagging what changed on site. Read how the company started on the about page.

Start With One of Your Own Jobs

See how a schedule runs alongside the field reports and budget.

What Is Construction Scheduling Software?

Construction scheduling software, also called construction project scheduling software, is a program for planning the order and timing of work on a construction job and keeping that plan current as the job moves. A construction schedule built in it usually has six parts.

Activities
The tasks that make up the project scope.
Durations
How long each activity is expected to take.
Dependencies
The links that tie one activity’s start or finish to another’s.
Milestones
Fixed dates for major events, such as dry-in or substantial completion.
Critical path
The chain of activities that sets the earliest finish date.
Baseline
The approved plan that progress is measured against.

Online construction scheduling software keeps the schedule on the web, so the office and the field open the same version. Construction management scheduling software also keeps it with the rest of the project’s records.

Construction Scheduling Methods Compared

Construction scheduling methods differ in what they show and who works from them, and most jobs use more than one. Construction scheduling tools often support only some of the five below, so check the list when you compare construction scheduler software.

MethodWhat It ShowsWho Works From ItWhen It FitsIn Shackleton
Gantt chartActivities as bars against a calendarProject managers, ownersShowing the whole job at a glanceYes
Critical path method (CPM)The chain of activities that sets the finish dateSchedulers, project managersJobs with many dependent activitiesYes
Three-week look-aheadThe next three weeks of work, drawn from the master scheduleSuperintendents, subcontractorsWeekly coordination in the fieldYes
Pull planningA sequence the trades build together, working back from a milestoneTrade partners, superintendentsThe start of a phaseNo
Line of balanceThe rate repeated work moves through units or floorsProject managersRepeated scopes such as multifamily floors or retail rolloutsNo

Shackleton covers the first three: Gantt charts, the critical path, and three-week look-aheads.

What to Prepare Before Moving Your Construction Schedule

A construction schedule moves into Shackleton faster with four things ready before onboarding starts, whether it lives today in Microsoft Project, a PDF, or other construction planning tools.

  • Baseline and Milestones

    The current schedule file, so your construction project schedule software starts from the dates you have committed to the owner.

  • Subcontractor List

    Each trade on the job, with a current contact.

  • Open RFIs and Change Orders

    Anything that could move the next three weeks of work.

  • Look-Ahead Owner

    The person who updates each trade’s look-ahead every week.

Frequently Asked Questions

What Is a Three-Week Look-Ahead Schedule?

A three-week look-ahead is a rolling plan of the next three weeks of work, drawn from the master schedule and usually updated weekly. Superintendents use it to confirm crews, materials, and inspections are lined up before the work starts.

What Is the Critical Path in a Construction Schedule?

The critical path is the longest chain of dependent activities in a schedule, and it sets the earliest date the job can finish. A delay to any activity on it delays the finish unless the work is re-sequenced. Activities off the critical path have float, meaning time they can slip without moving the finish date.

How Do You Build a Construction Schedule?

List the activities in the scope, estimate how long each takes, and link each one to the activities it depends on. Then set milestones, save the result as the baseline, and update it as work is completed. Most construction scheduling programs follow this order.

Does Shackleton Have a Construction Scheduling App for the Field?

Yes. On the iOS and Android app, superintendents view and update the schedule and each subcontractor’s look-ahead from the jobsite, and file each day’s report and site photos alongside them.

Is There Free Construction Scheduling Software?

Free construction schedule software can draw a Gantt chart, and a spreadsheet can hold a simple schedule. Paid construction scheduling software programs add the critical path and look-aheads. Shackleton is one of them, and it also ties the schedule to each job’s field reports and budget.

How Often Should a Construction Schedule Be Updated?

Most contractors update the master schedule at least once a month, often in step with the pay application. Each update records actual progress against the baseline, which shows which activities have slipped and whether the critical path has moved.

Can I Import My Existing Schedule?

Yes. Shackleton imports schedules from Microsoft Project or any schedule PDF, so a job already planned elsewhere doesn’t have to be rebuilt by hand.

Keep the Schedule With the Rest of the Job

One system for the master schedule, the look-aheads, the field record, and the budget.